New Construction of Domino 67 - St. Moritz

Project Data

 

Customer: Rhätische Bahn AG
Reference: Urs Deragisch
Location: St. Moritz
Contract:New Security System as Part of the Total Reconstruction of St. Moritz Station
Cost: 5.18 Million CHF
Start:October 2013
Commissioning:20. October 2015
Project Manager: Martin Bürgin

 

Our Contract

 

Construction of a new Relay Interlocking Type Domino 67, which is remotely controlled via RCI-Interface from the Landquart control centre.

Our Services

 

  • Planning
  • Project Planning for Indoor and Outdoor Facilities
  • Field Installation of Indoor and Outdoor Equipment
  • Factory test
  • Review
  • Commissioning

Specific Highlights

 

For the staging of the FIS World Ski Championships in February 2017, the St. Moritz railway station had to be completely rebuilt and made more user-friendly. To meet this requirement, the new Interlocking System had to be put into operation by the end of October 2015. For the total refurbishment of St. Moritz station, a total of 12 extension phases in both the old and the new Interlocking System were necessary.

Product Quantity Structure

19Main Signals
2Advance Signals
34Dwarf Signals
24Points
44Track Vacancy Detection Sections (Track Circuits UGSK 3)
1Catenary line changeover

         

© 2020 BÄR Bahnsicherung AG. All Rights Reserved.